Kametstal

facebook.com
Kametstal carries out major repairs of turbogenerator №4

The stability of the company's own electricity generation depends on the stability of the unit's operation

Facebook
Kametstal carried out major repairs of the cooling tower in May

Specialists carried out a complete diagnosis of this important technological node

facebook.com
Kametstal carried out a major overhaul of the equipment of the railcar dumper

During the repair, the steel structures of the sections of the rail track were replaced with subsequent concreting

facebook.com
Kametstal resumed the operation of the rolling mill after a long period of downtime

The rolling stock companies began to fulfill the order for the produce of 3,200 railcar axles for railcar builders of Ukraine

facebook.com
Kametstal set up new bottling technology at grade CCM №1

It is used for casting billets with a cross section of 160x160 mm made of steel C72D2 and C80D2 and 200x200 mm made of steel S3355

facebook.com
Kametstal started the repair of the T4-5 overhead power line

The length of the T4, T5 line is almost 2 km and is one of the longest at the plant

facebook.com
Kametstal will accumulate coke gas for use in production

The plant has already started implementing the relevant investment project

Facebook
Kametstal has completed the overhaul of the SM-6000 centrifugal compressor

The purpose of the repair is to increase the period of trouble-free operation of the unit, its performance indicator

Facebook
Kametstal has completed overhaul of the compressor in the oxygen compressor shop

The repairmen restored the main equipment and replaced the worn parts

facebook.com
Kametstal launched a new casting crane in the converter shop

The machine will be used for pouring liquid pig iron into converters, loading scrap metal and moving cargo

facebook.com
Kametstal purchased generators to provide the cooling system for the blast furnace

This will ensure a stable process of blast furnace melting and cooling of hot blast lances in blast furnaces

Kametstal performs the third stage of coke battery transfer №5

Specialists have already restored 12 walls, 4 more will be repaired