ArcelorMittal warned of delays in the supply of rolled steel in Europe

ArcelorMittal has informed customers that there may be delays in deliveries of flat products across Europe due to fires that occurred at the company’s facilities in Spain and France and affected two blast furnaces. Argus.Media informs about it.

“We must acknowledge that delays in execution of existing orderbook are likely to be unavoidable and that allocations for fresh orderbook may also be reduced,” the letter to clients said.

The letter was sent by ArcelorMittal’s European Flat Carbon division because the accidents affected furnaces that mainly produce pig iron for slab and flat products. It added that a «dedicated task force» had been set up to reduce the impact of these incidents.

ArcelorMittal was going to make up for the shortage of slabs from its Gijón (Spain) plant with material from Dunkirk (France), but those plans will apparently have to be revised. It may take several weeks for the company to return to normal production at the Flat Carbon Europe division. The damage and the time required for repairs are currently being assessed.

On March 22, 2023, due to the fire, ArcelorMittal stopped blast furnace A at the Gijon plant in northern Spain. The BF was restarted at the beginning of February 2023 after being idle since September 2022. As of the end of March, the company started inspection and cleaning of the affected blast furnace. ArcelorMittal said that it has not yet been determined how long BF-A will be out of service. According to local media, the blast furnace will be shut down for at least two months. Blast furnace B at the enterprise continues to work normally.

ArcelorMittal Dunkirk will work temporarily on one of the three blast furnaces after the fire at BF №4 that occurred on March 30. It is noted that BF №4 was not damaged as a result of the fire, the workers were evacuated, and there were no casualties. But during the investigation of the origin of the explosion, the plant will operate with only one blast furnace. Blast furnace №4 is the most powerful at the Dunkirk plant. This incident adds to the shortage in the hot-rolled steel market in the European Union, which is likely to affect prices and order fulfillment times.

As GMK Center reported earlier, force majeure is still valid regarding the condition of cold rolling mill №21 at the Tata Steel Nederland steel plant in Eimeiden, which the company announced on February 24, 2023. Problems arose during its modernization, which led to the extension of the commissioning phase. A task force was created to resolve the situation, and mitigation measures are being taken.

Share
Published by
Halina Yermolenko
Tags: ArcelorMittal Spain France rolled steel production
  • Global Market

Germany increased steel production by 8.9% y/y in 1H2026

In the first half of this year, Germany increased its steel production by 8.9% year-on-year…

Tuesday July 21, 2026
  • Global Market

Steel Dynamics increased its profit to $534 million in the second quarter

According to its second-quarter results, US steelmaker Steel Dynamics’ net revenue rose by a third…

Tuesday July 21, 2026
  • Global Market

China saw its stainless steel exports fall by 17.6% y/y in 1H2026

In the first half of 2026, China reduced its stainless steel exports by 17.6% year-on-year…

Tuesday July 21, 2026
  • Companies

Liberty Steel is placing staff at its Illinois plant on compulsory leave

The steel company Liberty Steel is temporarily placing employees at its wire rod production plant…

Tuesday July 21, 2026
  • Global Market

The global hot-rolled coil market remained stable in July against a backdrop of a seasonal lull

The global hot-rolled coil market showed mixed trends in July 2026. In the US, prices…

Tuesday July 21, 2026
  • Global Market

ArcelorMittal is raising prices for long products in Europe by €25 per tonne

ArcelorMittal, Europe’s largest steel producer, has announced a price increase for long products. The cost…

Tuesday July 21, 2026