Voestalpine has started work on the construction of EAF at the plant in Linz

The Austrian steel producer voestalpine, as part of the greentec environmental project, has started work on the construction of an electric arc furnace (EAF) at the company’s plant in Linz. This is stated in the press release of voestalpine.

«Only a few weeks after the official start of the construction of the new EAF at the voestalpine plant in Donavwitz, today the foundation of the electric arc furnace is being laid in Linz as part of the greentec project,» the message says.

The construction of the EAF in Linz will begin in 2024, and the commissioning of the facility is planned for 2027. The capacity of the unit is estimated at 1.6 million tons of steel with a reduced CO2 content per year. To maintain the high quality of products, the furnace will operate using a mixture of scrap, pig iron and hot briquetted iron (HBI) as raw materials. Investments in the project are estimated at €1 billion.

At the first stage of the greentec project, the company plans to replace two blast furnaces at the factories in Linz and Donawitz with high-tech electric arc furnaces. By electrifying energy-intensive steel production processes, the company plans to reduce CO2 emissions by approximately 30% from 2027, which is equivalent to an annual reduction in emissions of almost 4 million tons.

The second stage of greentec involves the start of construction of two more EAFs in Linz and Donawitz, as well as additional investments in the development of the plant in Linz. Thus, by 2050, the company plans to achieve zero emissions. For this, research into new ways of steel production and investments in pilot projects are being carried out.

«The two laying ceremonies of electric arc furnaces in Linz and Donawitz are more than just a symbolic act and the beginning of a construction project. They are a visible cornerstone of voestalpine’s green future and an important milestone for climate protection in Austria,» comments Herbert Eibensteiner, CEO of voestalpine.

The volume of investments in both projects is €1.5.

As GMK Center reported earlier, the developer of advanced technologies in decarbonization Compact Membrane Systems (CMS) together with voestalpine announced the launch pilot project on carbon capture Optiperm carbon. It will start operating in the fourth quarter of 2023 at the steel company’s plant in Linz.

  • Industry

Consumption of steel products in Ukraine increased to 1.2 million tons in January-April

In January-April 2025, Ukraine increased its consumption of steel products (rolled products and semi-finished products)…

Wednesday May 14, 2025
  • Companies

DMZ presents environmental modernization plan with a focus on decarbonization

Dnipro Metallurgical Plant (DMZ), part of DCH Steel, has presented a comprehensive strategy for environmental…

Wednesday May 14, 2025
  • Global Market

India increased production of iron ore pellets by 5% y/y in FY2024/2025

In FY2024/2025, India increased production of iron ore pellets to 105 million tons, up 5%…

Wednesday May 14, 2025
  • Companies

Electricity cost and tariffs force Ingulets Mining to continue downtime

Ingulets Mining and Processing Plant (Ingulets GOK), a part of Metinvest Group, continues to be…

Wednesday May 14, 2025
  • Global Market

EU exported 3 million tons of scrap in January-February

In January-February 2025, EU companies specializing in ferrous scrap operations reduced their exports of raw…

Wednesday May 14, 2025
  • Global Market

UK TRA recommends restricting countries’ access to residual quotas on steel imports

The British Trade Remedies Authority (TRA) has recommended introducing restrictions on the share of total…

Wednesday May 14, 2025