The Central Mining and Processing Plant (Central GOK) of the Metinvest Group completed the overhaul of the OK-324 roasting machine at the clod factory. This is stated in the press release by Metinvest.Media.

During the repair, specialists updated the machine horn and replaced the refractory lining. To do this, the pre-chambers were covered with fire-resistant bricks of the Slovak firm REFRAKO and Zaporizhvognetryv. The total amount of material for these works is estimated at 100 tons.

To reduce the environmental burden and increase energy efficiency, the gas ducts of the D-5 smoke extractor were repaired with the replacement of pockets. Also, the D-2 smoke extractor pipe was replaced and the D-2 droplet catchers were repaired. This will contribute to the improvement of the fume hood and effective cleaning of the gas stream from dust.

A new rotor was installed on the D-1 smoke extractor, which is an important part of the OK-324 roasting machine. This device takes the heated gases from the cooling zone and supplies them to the drying zone, which contributes to the efficient drying process of the pellets before the thermosetting process.

In addition, four conveyor belts on conveyors OB 6-7, KP 2-7, OB 7, OB 4-7 were replaced as part of the overhaul.

«For uninterrupted production of high-quality products, we replaced and repaired components and mechanisms that cannot be carried out during factory operation. In two weeks, the experts carried out work to diagnose the serviceability of all systems and units, of which there are more than 200 at the factory. Thanks to effective measures, the entire complex of factory equipment is ready to work with high reliability and productivity until the next scheduled overhaul,» said the head of the Central GOK coagulation factory Andriy Zhilkinskyi.

As GMK Center reported earlier, the Central GOK installed modernized a bowl flocculator in a flocculation plant to ensure a stable pellet production process.

  • Infrastructure

Businesses purchased the entire volume of electricity at the first long-term auctions

The first electricity auctions under the new long-term contract mechanism have taken place in Ukraine.…

Monday July 13, 2026
  • Global Market

India has extended the anti-dumping duty on imports of seamless pipes from China

India has extended the anti-dumping duty on imports of seamless pipes, tubes and hollow sections…

Monday July 13, 2026
  • Companies

Jingye Steel will insist on full compensation for the takeover of British Steel

China’s Jingye Steel has stated that it will demand prompt, adequate and effective compensation from…

Monday July 13, 2026
  • Global Market

EU decision on steel quotas poses further challenges for Ukraine – Politico

On 1 July, new EU safeguard measures on steel came into force after the European…

Monday July 13, 2026
  • Global Market

JSW Italy has reached an agreement with the Italian government on the development of the Piombino steelworks

The Italian Ministry of Economic Development (Mimit) has reached an agreement with JSW on the…

Monday July 13, 2026
  • Global Market

Baosteel is raising prices for hot-rolled steel for August sales

Baoshan Iron & Steel (Baosteel), a subsidiary of the world’s leading steel producer China Baowu…

Monday July 13, 2026