Kametstal completed the testing of the foundry crane produced by NKMZ

Kametstal Iron and Steel Works has successfully completed running tests of a new foundry crane in the converter shop. The unit is produced at the Novokramatorsky Mashinobudivny Zavod (NKMZ). The company’s press service reports about it on the Facebook page.

“Despite the war, our Steel Front is confidently holding on. A production renewal program is underway at Kametstal. Foundry crane №12 was tested in the converter workshop. The assembly work of the new multi-ton structure lasted for several months,” the message says.

The tests were carried out under the supervision of experts and a representative of NKMZ. First, the new crane was subjected to static tests – lifting and fixing a load weighing 400 tons. After that, dynamic tests were carried out with the movement of the load.

At the stage of start-up and adjustment works, the shop staff was trained in the operation, maintenance and repair of this crane.

Foundry crane №12 is designed for pouring hot pig iron into the converter. It will also fill scrap metal into the converter and move cargo. The unit has modern energy-efficient equipment, which will allow to reduce electricity consumption, maintenance costs, as well as to improve the working conditions of the staff.

“Such a crane is the most convenient and easy to operate for a driver. In addition, the cabin has a wide panoramic view and a window made of armored glass, which guarantees increased work safety. Also, the workplace is equipped with a winter-summer air conditioner, which will maintain a comfortable temperature for the employee at any time of the year,” the plant notes.

As GMK Center reported earlier, Kametstal for the first time cast the cone and ring of the backfill apparatus’ bowl of the BF weighing 18 tons and 9 tons, respectively. The cast elements will be sent to the Zaporizhzhia Foundry and Mechanical Plant (ZFMP) for further processing and assembly of the backfill apparatus. After that, the structure will be installed on the blast furnace of the enterprise.

Before, the plant shipped the first batch of high-grade liquid argon to a third-party consumer in the amount of 19.5 tons. The plant reduced gas consumption in production, which made it possible to accumulate and ship it to the country’s market.

  • Infrastructure

Tosyalı has raised €187 million for a solar power development project

The Spanish bank BBVA has provided the Turkish steel group Tosyalı with €187 million in…

Tuesday July 14, 2026
  • Global Market

China’s steel exports fell by 5.6% y/y in January–June

In the first half of 2026, China’s steel exports fell by 5.6% year-on-year to 54.87…

Tuesday July 14, 2026
  • Global Market

Tokyo Steel has left its prices for steel products unchanged for August sales

Tokyo Steel, a leading Japanese electric arc furnace steel producer, has left its prices for…

Tuesday July 14, 2026
  • Global Market

The EC has approved €63 billion in aid for France’s offshore wind energy sector

The European Commission has approved a €63 billion French government programme aimed at supporting the…

Tuesday July 14, 2026
  • Green steel

China has unveiled a new plan to reduce carbon emissions by 2030

At the end of last week, China published an Action Plan to reach peak carbon…

Tuesday July 14, 2026
  • Global Market

Nucor has resumed raising prices for hot-rolled coils

The American steel producer Nucor has once again raised its spot price (CSP) for hot-rolled…

Tuesday July 14, 2026