Central Mining updated the equipment of the clod plant

The Central Mining and Processing Plant (Central GOK) has installed a modernized bowl-type flocculator at the clod plant to ensure a stable pellet production process. This is stated in the Metinvest. Media’s press release.

“Over the past year, the staff of the Central GOK has proven its professionalism and ability to work effectively even in wartime conditions. Despite the difficulties, the company continued to update its production facilities. In particular, specialists managed to overhaul the equipment of the OK-324 clod plant and roasting machine,” the message reads.

One of the important projects implemented at the end of last year was the installation of the ОCH-7500 bowl clod maker. It was placed in the embankment building to replace one of the six that had developed its resource.

The new equipment has a number of advantages: a rigid holding structure, a unique support bearing and the ability to adjust the angle of bowl’s inclination. Its commissioning will allow the enterprise to maintain production at the required level.

After testing the equipment, at the end of 2022, the first experimental batch of raw pellets came off the conveyor for firing. As plant’s specialists note, the stabilization of the process of raw clods is due to the ability to adjust both the frequency of bowl’s rotation and the change in its angle of inclination.

Currently, the equipment is working at full load and meets the specifications.

“The modernization of the equipment of the clod plant, together with a set of measures to improve the quality of pellets, is one of the key projects of 2022, which we successfully implemented at the Central GOK. This will significantly increase production volumes. Even in such a difficult time, the team of Central GOK makes every effort to preserve the existing sales markets, as well as to win new ones by expanding the range and high quality of our products,” noted the CEO of Cwntral GOK Dmytro Shevchyk.

As GMK Center reported earlier, at the beginning of November 2022, the Central GOK began overhaul equipment at the clod plant. The work on its restoration is designed to ensure uninterrupted production of pellets with a high iron content. In total, more than 200 units of factory equipment were subject to maintenance.

Share
Published by
Masha Malonog
Tags: capital investment pellets Metinvest Central GOK
  • Industry

China to support a series of low-carbon demonstration projects

China's National Development and Reform Commission (NDRC) has identified the first list of low-carbon demonstration…

Monday May 6, 2024
  • Global Market

Steel demand in India to grow by 8-10% in FY2024/2025 – Tata Steel CEO

Demand for steel in India in fiscal year 2024/2025 (ending in March 2025) will grow…

Monday May 6, 2024
  • Global Market

Electrical steel becomes a key product in China’s steel industry

Global decarbonization is turning electrical steel into one of the key products of China's ferrous…

Friday May 3, 2024
  • Global Market

UAE and Oman agree on a $32 billion green megaproject

The United Arab Emirates (UAE) and Oman have signed an investment agreement worth AED 117…

Friday May 3, 2024
  • Global Market

Germany imported 155 thousand tons of steel from third countries in January-February

In January-February 2024, Germany increased its imports of rolled steel products from third countries by…

Thursday May 2, 2024
  • Global Market

Belgium reduced steel production by 5.7% y/y in March

Belgian steelmakers reduced steel production by 5.7% in March 2024 compared to March 2023, to…

Thursday May 2, 2024