Central Mining completed the planned replacement of the mill at the iron ore processing plant

The Central Mining and Processing Plant (Central GOK) carried out the planned replacement of the MSHC 161 mill at the production site for the repair of technological equipment of the iron ore processing plant. This is stated in the press release of Metinvest.Media.

“The mills are used in the production of concentrate, the equipment is designed for grinding magnetite quartzite. The final quality of the concentrate depends on their work, so concentrators closely monitor the operation of the equipment – they carry out scheduled repairs and maintenance,” the message says.

During the repair, specialists replaced the armor, loading nozzle, feeder housing, scoops and slide bearings. The entire process of replacing the layer mill and its components was carried out in just 24 hours, which allowed the factory to operate as planned.

Thanks to the re-equipment, the equipment will be able to work without accidents for the next 104 days – until the first planned and preventive maintenance.

“At Central GOK, the Metinvest Group continues to systematically update equipment to control product quality and ensure uninterrupted operation of the enterprise,” the company summarizes.

As GMK Center reported earlier, Central GZK repaired four vibratory feeders of the crushing plant. The production capacity of modernized equipment is up to 2.5 thousand tons per hour.

Also, Central GOK allocated UAH 3.2 million for the renewal of railway tracks on the race section, which is involved in the transportation of iron ore from the Petrivskyi and Artemivskyi quarries to the enterprise’s industrial site.

  • Global Market

Austria increased steel production by 19.1% m/m in March

Austrian steelmakers increased steel production by 19.1% in March 2024 compared to February this year,…

Tuesday May 7, 2024
  • Companies

Kametstal has shipped 160 thousand tons of rolled products from mill 400/200 since the beginning of the year

Since the beginning of 2024, Kametstal has shipped almost 160 thousand tons of products produced…

Tuesday May 7, 2024
  • Industry

China to support a series of low-carbon demonstration projects

China's National Development and Reform Commission (NDRC) has identified the first list of low-carbon demonstration…

Monday May 6, 2024
  • Global Market

Steel demand in India to grow by 8-10% in FY2024/2025 – Tata Steel CEO

Demand for steel in India in fiscal year 2024/2025 (ending in March 2025) will grow…

Monday May 6, 2024
  • Global Market

Electrical steel becomes a key product in China’s steel industry

Global decarbonization is turning electrical steel into one of the key products of China's ferrous…

Friday May 3, 2024
  • Global Market

UAE and Oman agree on a $32 billion green megaproject

The United Arab Emirates (UAE) and Oman have signed an investment agreement worth AED 117…

Friday May 3, 2024