The Central Mining and Processing Plant (Central GOK) carried out the planned replacement of the MSHC 161 mill at the production site for the repair of technological equipment of the iron ore processing plant. This is stated in the press release of Metinvest.Media.

“The mills are used in the production of concentrate, the equipment is designed for grinding magnetite quartzite. The final quality of the concentrate depends on their work, so concentrators closely monitor the operation of the equipment – they carry out scheduled repairs and maintenance,” the message says.

During the repair, specialists replaced the armor, loading nozzle, feeder housing, scoops and slide bearings. The entire process of replacing the layer mill and its components was carried out in just 24 hours, which allowed the factory to operate as planned.

Thanks to the re-equipment, the equipment will be able to work without accidents for the next 104 days – until the first planned and preventive maintenance.

“At Central GOK, the Metinvest Group continues to systematically update equipment to control product quality and ensure uninterrupted operation of the enterprise,” the company summarizes.

As GMK Center reported earlier, Central GZK repaired four vibratory feeders of the crushing plant. The production capacity of modernized equipment is up to 2.5 thousand tons per hour.

Also, Central GOK allocated UAH 3.2 million for the renewal of railway tracks on the race section, which is involved in the transportation of iron ore from the Petrivskyi and Artemivskyi quarries to the enterprise’s industrial site.

  • Infrastructure

China will continue to build coal-fired power plants until 2027

China plans to continue building coal-fired power plants until 2027 in regions where they are…

Saturday April 19, 2025
  • Global Market

Italy reduced rolled steel exports by 12% y/y in January

In January 2025, Italian steel enterprises reduced exports of rolled steel products to third countries…

Saturday April 19, 2025
  • Companies

Emsteel increased spending on innovation and investment by 127% in 2020-2024

Emsteel, one of the largest publicly traded steel and building materials producers in the Gulf…

Saturday April 19, 2025
  • Companies

Ferrexpo maintains capital expenditures at $102 mln in 2024

In 2024 capital expenditures of Ferrexpo, the London-listed iron ore producer with operations in Ukraine,…

Friday April 18, 2025
  • Global Market

European prices for hot rolled coils increased in the first half of April

Prices for hot-rolled coils in the Nordic region rose by €10/t in the first half…

Friday April 18, 2025
  • Global Market

EU HRC prices rise, but market remains volatile – WSD

European producers are trying to increase prices for hot rolled coil (HRC) amid limited supply…

Friday April 18, 2025