Zaporizhstal Iron and Steel Works launched its blast furnace No. 2 following its overhaul repair in the framework of the production modernization program.
According to the company, the overhaul lasted for 43 days. The investment amounted to around UAH 220 million.
The repair works included replacement of the charging system and partial replacement of shell, shotcreting and lining of the shaft, replacement of metal structures and refractory coating of the main runner.
Around 2 thousand tons of refractory materials were used for the purposes of the overhaul.
Moreover, Zaporizhstal repaired the cooling system and partially replaced spent pig iron staves with copper and steel ones.
The repair works also included some environmental protection measures. Thus, the company repaired the key elements of the aspiration system to bring the production process in compliance with the current environmental standards of Ukraine.
Over 400 workers of Zaporizhstal itself and contractors were engaged in the overhaul of the blast furnace No. 2.
Metinvest and Zaporizhstal built a highway in Zaporizhzhia worth UAH 220 million.
How Zaporizhstal is preparing for the construction of the basic oxygen furnace shop
Global decarbonization is turning electrical steel into one of the key products of China's ferrous…
The United Arab Emirates (UAE) and Oman have signed an investment agreement worth AED 117…
In January-February 2024, Germany increased its imports of rolled steel products from third countries by…
Belgian steelmakers reduced steel production by 5.7% in March 2024 compared to March 2023, to…
In 2023 Ferrexpo, the London listed iron ore company with assets in Ukraine, emitted 384…
In 2023 Ferrexpo, the London listed iron ore company with assets in Ukraine, recorded zero…