Zaporizhstal repaired its blast furnace No. 2

Zaporizhstal Iron and Steel Works launched its blast furnace No. 2 following its overhaul repair in the framework of the production modernization program. 

According to the company, the overhaul lasted for 43 days. The investment amounted to around UAH 220 million.

The repair works included replacement of the charging system and partial replacement of shell, shotcreting and lining of the shaft, replacement of metal structures and refractory coating of the main runner. 

Around 2 thousand tons of refractory materials were used for the purposes of the overhaul. 

Moreover, Zaporizhstal repaired the cooling system and partially replaced spent pig iron staves with copper and steel ones.

The repair works also included some environmental protection measures. Thus, the company repaired the key elements of the aspiration system to bring the production process in compliance with the current environmental standards of Ukraine.

Over 400 workers of Zaporizhstal itself and contractors were engaged in the overhaul of the blast furnace No. 2.

Metinvest and Zaporizhstal built a highway in Zaporizhzhia worth UAH 220 million.

How Zaporizhstal is preparing for the construction of the basic oxygen furnace shop

Share
Published by
Kira Ivanova
Tags: Запоріжсталь capital investment
  • Global Market

Global steel production rose by 1.7% y/y in June

Global steel production in June 2026 rose by 1.7% year-on-year – to 155.7 million tonnes.…

Thursday July 23, 2026
  • Global Market

Kardemir Çelik is launching an IPO to raise working capital

The Turkish steelmaker Kardemir Çelik Sanayi A.Ş. has announced that it is preparing to enter…

Thursday July 23, 2026
  • State

The ECA supported Ukrainian exports to the tune of 7.5 billion UAH in 1H2026

The Export-Credit Agency of Ukraine (ECA) supported exports of Ukrainian goods worth 7.53 billion UAH…

Thursday July 23, 2026
  • Global Market

The EC has rejected proposals to protect exporters under the CBAM

The reform of the Emissions Trading Scheme (ETS) proposed by the European Commission has failed…

Thursday July 23, 2026
  • Global Market

Vale increased ore production by 1% y/y in Q2

The Brazilian mining company Vale has published its report for the second quarter of 2026.…

Thursday July 23, 2026
  • Global Market

The Brazilian government is to allocate $3.7 billion to support businesses in the wake of the new 25% US tariffs

The Brazilian government has announced the allocation of 18.5 billion reais ($3.66 billion) to support…

Thursday July 23, 2026