Zaporizhstal Iron and Steel Works launched its blast furnace No. 2 following its overhaul repair in the framework of the production modernization program.
According to the company, the overhaul lasted for 43 days. The investment amounted to around UAH 220 million.
The repair works included replacement of the charging system and partial replacement of shell, shotcreting and lining of the shaft, replacement of metal structures and refractory coating of the main runner.
Around 2 thousand tons of refractory materials were used for the purposes of the overhaul.
Moreover, Zaporizhstal repaired the cooling system and partially replaced spent pig iron staves with copper and steel ones.
The repair works also included some environmental protection measures. Thus, the company repaired the key elements of the aspiration system to bring the production process in compliance with the current environmental standards of Ukraine.
Over 400 workers of Zaporizhstal itself and contractors were engaged in the overhaul of the blast furnace No. 2.
Metinvest and Zaporizhstal built a highway in Zaporizhzhia worth UAH 220 million.
How Zaporizhstal is preparing for the construction of the basic oxygen furnace shop
In January-May 2025, Ukrainian steel companies increased their exports of long rolled steel by 43.3%…
The industrial company Interpipe shared its experience of reintegrating veterans at the HR Wisdom Summit…
The Ukrainian Union of Industrialists and Entrepreneurs (USPP) has appealed to the Cabinet of Ministers…
Steel market participants and industry observers warn that the new EU state aid framework program…
In January-May 2025, Ukrainian steelmakers increased imports of coke and semi-coke (HS 2704) by 39.9%…
In May 2025, US steelmakers shipped 7.51 million net tons of steel, up 1% from…