Kametstal Iron and Steel Works has put blast furnace No. 9 back into operation after a major overhaul. This is stated in the company’s statement.

The repair contractors completed the primary task of restoring the refractory lining of the furnace and the upper roof of the furnace with the replacement of four cooling plates.

In addition, the shutdown of the unit was productively used to repair equipment in key areas of the blast furnace. In particular, Zaporizhvognetryv’s specialists repaired the refractory lining of the hot blast duct, while the specialists of the Central Repair and Maintenance Department and Metinvest Promservice replaced the fans of the air heaters and the equipment for opening and closing the cast iron tundish in the casting yard.

Another important set of works was the upgrade of the BF loading equipment. Some steel structures and top loading equipment were replaced and the inclined bridge was repaired.

‘Thanks to the joint team efforts of the contractors and the blast furnace repair service, we completed the overhaul of BF No. 9 in a timely manner, thereby ensuring its continued stable operation to meet the planned pig iron production targets for the entire technological interval until the next scheduled overhaul,’ said Evgeny Podgorny, Deputy Head of Blast Furnace Shop for Engineering at Kametstal.

In September 2024, Kametstal carried out an accelerated overhaul of blast furnace No. 1M. The main task was to restore the refractory lining of the unit’s air heater block and replace the water-cooling elements of metal structures and hot blast valves.

Share
Published by
Halina Yermolenko
Tags: maintenance Kametstal blast furnance production
  • Companies

Voestalpine forecasts a rise in profits amid new EU protective measures

Austrian steel producer voestalpine expects profits to rise in the 2026/2027 financial year against the…

Wednesday June 3, 2026
  • Global Market

Billet prices rose by $10–20 per ton in regional markets in May

In most regional billet markets, prices rose slightly in May—by $10–20 per ton. The Gulf…

Wednesday June 3, 2026
  • Global Market

Iron ore prices fell by 3% in May

Iron ore prices (KORE 62% Fe/Qingdao) began to decline in late May–early June 2026 following…

Wednesday June 3, 2026
  • Industry

Ukraine increased imports of long steel products by 56.6% y/y in January–April

In January–April 2026, the long steel market in Ukraine saw a significant increase in imports—up…

Wednesday June 3, 2026
  • Industry

Railway disruptions pose risks for German steelmakers

German steelmakers have warned that prolonged disruptions in rail freight transport threaten the supply of…

Wednesday June 3, 2026
  • Companies

Marcegaglia is increasing its investment in the project in Fos-sur-Mer

The Italian group Marcegaglia is investing an additional €600 million in the Mistral project in…

Wednesday June 3, 2026