Kametstal completed the overhaul of turbogenerator №4

Kametstal Iron and Steel Works improves energy security under martial law. The plant’s power engineers have completed a major overhaul of a powerful turbine generator No. 4 to generate its own electricity. This is stated in the company’s message.

Scheduled post-repair tests are currently underway to identify and work out all possible comments before putting the unit into operation.

The main efforts during the repair were aimed at restoring the technical parameters of the unit’s rotors. In particular, on the turbine’s high-pressure rotor, contractors replaced all impeller blades and restored seals to eliminate unproductive steam leaks. The technical regulations for the low-pressure rotor were met. As a result, the turbine’s efficiency was brought as close to the design as possible.

In addition, the generator rotor was repaired: insulation was restored, the banding rings were repaired, and the rotor and stator were painted.

In the course of the work, both rotors of turbogenerator No. 4 were qualitatively balanced – the tests did not reveal any comments regarding permissible vibrations.

Specialists also repaired the entire array of TG auxiliary equipment – water and oil pumps, ejectors, low-pressure heater.

«Energy engineers take into account previous experience and aim to ensure the armor of the enterprise’s power supply even in the event of its possible emergency shutdown due to enemy shelling, as was the case last winter, in order to prevent damage or destabilization of the main metallurgical equipment due to a sudden blackout. The successful overhaul of the powerful turbogenerator No. 4 is primarily aimed at fully restoring its resource and bringing production capabilities up to passport parameters,» the message states.

As GMK Center reported earlier, Kametstal recently completed overhaul of converter №1. At the final stage, one of the key components of the unit was replaced – the bearing of the non-drive trunnion. This part weighing 5.4 tons ensures the rotation of the converter housing during the technological process of steel smelting.

  • Companies

Celsa considers selling Polish plant Huta Ostrowiec

Spanish steelmaker Celsa ended 2024 with losses of €281 million and is considering selling its…

Tuesday July 1, 2025
  • Global Market

Nucor raised prices for hot-rolled coil by $10/t

US steel company Nucor announced an increase in the weekly spot price (CSP) for hot-rolled…

Tuesday July 1, 2025
  • Companies

Central Mining modernized its pelletizing plant at a cost of UAH 40 million

A three-week repair campaign costing almost UAH 40 million has been completed at the pelletizing…

Tuesday July 1, 2025
  • Companies

SSAB has secured an additional €430 million for its green transformation in Luleå

Swedish steel company SAAB has announced that it has secured an additional €430 million in…

Tuesday July 1, 2025
  • Industry

Ukraine reduced semi-finished products’ exports by 34% y/y in January-May

In January-May 2025, Ukrainian steel companies reduced exports of semi-finished steel products by 34.1% compared…

Tuesday July 1, 2025
  • Society

Metinvest to allocate over $500 thousand to support veterans in 2025

Metinvest Group, which has faced the mobilization of one in five employees since the start…

Tuesday July 1, 2025