ArcelorMittal has started the overhaul of the air heater at blast furnace No. 6

ArcelorMittal Kryvyi Rih started overhaul of the air heater of blast furnace No. 6. This is stated in the press release of the newspaper Metallurgist.

The main thing that needs to be done during the repair is to restore the refractory lining of the air heater and its main components.

“This process is long and painstaking, because before the installation of new equipment, it is necessary to carefully get rid of the already spent lining,” the message says.

After dismantling the old parts and equipment, only the steel casing will remain. All other parts – hot blast valves, gas throttles, main control units of the air heater and other – will be replaced with new ones. Also, 3.9 thousand tons of new refractory masonry will be laid.

“The air required for fuel combustion in the blast furnace is preheated in air heaters before being fed into the tuyere. This saves fuel and increases the productivity of melting. Each blast furnace has an air heater of its own size. At BF No. 6, each of the four air heaters of the block has an almost 9-meter diameter, a total height of 49.3 m, with refractory masonry, a height of more than 40 m,” noted Yuri Kurylo, Head of blast furnace shop No. 1 with technology.

There is a plan to complete the overhaul in 210 days, and completion is expected in October. After the repair, the temperature of the hot blast into the furnace can be increased to 1030 °C, which will save fuel.

As GMK Center reported earlier, ArcelorMittal resumed after long downtime the work of the small-sized unit DS-250-5 for the production of rebar. On July 7, the heating of the furnace began, and on July 11, the first product was already received at the mill.

ArcelorMittal since July 2022 transferred a significant part of employees, including top management and foreign workers, by 2/3 of the workload due to the inability to pay salaries in full.

For this the plant completed the reconstruction slag yard No. 1 of the converter shop. As a result, the workshop actually received a new slag yard with new equipment and a comfortable change house.

  • Infrastructure

200 million tonnes of cargo have been transported via the Ukrainian maritime corridor

Since its launch in September 2023, the Ukrainian maritime corridor has already handled 200 million…

Thursday June 4, 2026
  • Global Market

The UK has announced the details of the transition period for steel safeguard measures

The UK Department for Business and Trade (DBT) has published details of a transitional phase…

Thursday June 4, 2026
  • Global Market

Canada will extend its tariffs on steel and aluminium imports for a further year

Canada will extend tariff rate quotas (TRQs) and preferential tariffs on imports of certain types…

Thursday June 4, 2026
  • Global Market

Global scrap consumption rose by 4.5% y/y in 2025 — BIR

Global scrap consumption rose by 4.5% compared with the previous year, reaching 480 million tonnes,…

Thursday June 4, 2026
  • Companies

Worthington Steel has completed the acquisition of Klöeckner

The US-based Worthington Steel has completed its voluntary public takeover bid for Klöeckner & Co…

Thursday June 4, 2026
  • Companies

Voestalpine forecasts a rise in profits amid new EU protective measures

Austrian steel producer voestalpine expects profits to rise in the 2026/2027 financial year against the…

Wednesday June 3, 2026