Zaporizhstal has invested UAH 370 million in the overhaul of its main units since the beginning of the year

Metinvest Group’s Zaporizhstal steelworks continues to implement its annual capital investment program aimed at supporting the stable operation of production facilities and environmental equipment. In 2025, the plant completed a large-scale repair of the main units in the blast furnace, open-hearth, and hot rolling shops. The total budget for the work was UAH 370 million, according to a press release.

According to the plant’s acting CEO, Taras Shevchenko, the main goal of the enterprise is to maintain production during the war and provide a basis for further modernization.

“Repairs and proper maintenance of production facilities are an important contribution to ensuring the stable operation of Zaporizhstal today and in the future,” he stressed.

The work was carried out continuously with the participation of more than 400 specialists from Zaporizhstal, Zaporizhogneupor, Kametstal, and a number of contracting organizations. In the blast furnace shop, the equipment of furnace No. 3 was restored: repairs were carried out on the cone-less charging apparatus, casting yard units, air heater equipment, as well as metal structures for charge feeding and the bunker trestle. Special attention was paid to gas cleaning: air ducts and dust collectors were cleaned and repaired, ensuring cleaning performance of 20 mg/m³.

In the open-hearth shop, a two-tank steel-making unit was repaired, in particular, the vault and working area of the furnace were refired using more than 800 tons of refractories, part of the supporting metal structures were replaced, and gas cleaning units were updated.

In the hot rolling shop, the modernization covered the Slabing-1150 and BTLS-1680 mills. Specialists repaired the universal cage, electric drives, roller tables, turntable units, as well as the units of the machine room and the winding section. Electrical equipment and power systems were inspected.

The completed repairs should increase the reliability of the units, reduce energy losses, and lower the level of product defects. In addition, in 2025, the company will allocate another UAH 75 million to upgrade key units of the combined heat and power plant.

Zaporizhstal’s total capital investment budget for this year will exceed UAH 1 billion.

As a reminder, as part of its 2024 investment program, the company allocated UAH 938 million to support its production capacities. In particular, the funds were invested in the overhaul of key production units and the implementation of investment projects in occupational safety, information technology, and the social sphere.

Share
Published by
Vadim Kolisnichenko
Tags: capital investment Zaporizhstal Ukraine’s iron and steel industry
  • Global Market

China’s steel exports fell by 5.6% y/y in January–June

In the first half of 2026, China’s steel exports fell by 5.6% year-on-year to 54.87…

Tuesday July 14, 2026
  • Global Market

Tokyo Steel has left its prices for steel products unchanged for August sales

Tokyo Steel, a leading Japanese electric arc furnace steel producer, has left its prices for…

Tuesday July 14, 2026
  • Global Market

The EC has approved €63 billion in aid for France’s offshore wind energy sector

The European Commission has approved a €63 billion French government programme aimed at supporting the…

Tuesday July 14, 2026
  • Green steel

China has unveiled a new plan to reduce carbon emissions by 2030

At the end of last week, China published an Action Plan to reach peak carbon…

Tuesday July 14, 2026
  • Global Market

Nucor has resumed raising prices for hot-rolled coils

The American steel producer Nucor has once again raised its spot price (CSP) for hot-rolled…

Tuesday July 14, 2026
  • Infrastructure

Businesses purchased the entire volume of electricity at the first long-term auctions

The first electricity auctions under the new long-term contract mechanism have taken place in Ukraine.…

Monday July 13, 2026