The nationalization of British Steel could cost the British government billions of pounds

The full nationalization of the troubled British Steel will cost taxpayers billions of pounds and will be “extremely expensive” for the British government, according to Politico.

According to a report by the National Audit Office, since taking control of the Scunthorpe facility 11 months ago, taxpayers have already spent £419 million to support the company. At the current rate, spending on British Steel could exceed £1.5 billion by 2028. Thus, a transition to full nationalization could become “extremely burdensome for the budget,” notes a senior representative of the steel industry.

British Steel will require even more funds if a decision is made to modernize the outdated plant in Scunthorpe and transform it into a modern facility with electric arc furnaces. Such a project would cost at least £1 billion and take at least five years to complete. In the absence of a private buyer, these costs would also fall on taxpayers.

Industry representatives see an opportunity to attract investors in this scenario if the government assumes British Steel’s obligations and merges it with Specialty Steel UK (SSUK), which already operates electric arc furnaces. This became possible after the government took control of the assets of the former Liberty Steel Group, which announced its liquidation last year.

Currently, Liberty owns the largest electric arc furnace, and there is stable demand for products for the aerospace, defense, and oil and gas sectors. In his view, it would be advisable to consolidate these capacities into a single asset. He also added: when it comes to national security, the state needs its own specialty steel for the production of military products.

As a reminder, the UK government plans to introduce a bill to Parliament that would grant it the right to place British Steel under state control, subject to a public interest test.

As reported by GMK Center, last April the government took control of British Steel to prevent the closure of the last two blast furnaces in the UK. Over nine months (from April 12, 2025, to January 31, 2026), the British government spent £377 million ($499 million) to keep the British Steel plant in Scunthorpe operational. The National Audit Office (NAO) reported that the company’s current operations cost the Department for Business and Trade approximately £1.3 million per day.

  • Global Market

Excess steel production capacity continues to weigh on global markets – OECD

By 2026, global excess steel production capacity will reach 745 million tons. This is according…

Thursday June 4, 2026
  • Industry

Ukraine reduced imports of steel coke by 2.1% y/y in January–April

In January–April 2026, Ukraine’s steelworks reduced imports of coke and semi-coke (HS Code 2704) by…

Thursday June 4, 2026
  • Industry

Industrial production fell by 0.4% y/y in January–April

Industrial production in Ukraine fell by 0.4% year-on-year in the January–April period. This is linked…

Thursday June 4, 2026
  • Global Market

Trump’s tariffs have significantly reduced steel exports from the EU to the US – EUROFER

Since the US raised steel tariffs to 50%, exports of steel products from the EU…

Thursday June 4, 2026
  • Global Market

Turkey increased steel exports by 11.3% y/y in April

In April, Turkey increased its steel exports by 11.3% year-on-year to 1.3 million tonnes. The…

Thursday June 4, 2026
  • Infrastructure

200 million tonnes of cargo have been transported via the Ukrainian maritime corridor

Since its launch in September 2023, the Ukrainian maritime corridor has already handled 200 million…

Thursday June 4, 2026