Northern Mining upgrades equipment at ore dressing plants No. 1-2

Metinvest Group’s Northern Mining and Processing Plant (Northern Mining) has completed the planned work at its ore dressing plants (ROF) No. 1 and 2 and slurry pumping station No. 1 during a three-day annual shutdown. It is reported by Metinvest.Media.

“We have started the planned shutdown of the slurry pumping station of the technical water supply and sludge management shop for repair. The main tasks include the replacement, repair, inspection and maintenance of pumping equipment, valves, water supply pipelines, etc.”, the statement said.

The main goal of the planned shutdown is to stabilize the operation of technical water supply systems. Particular attention is being paid to the equipment involved in this process, as its replacement is possible only if the processing complex – ROF No. 1, 2 and PCP No. 1 – is completely shut down. The plant’s specialists have diagnosed all the equipment in advance and identified what needs to be restored. To ensure efficient operation of the equipment, they planned the required amount of repairs to avoid further emergency downtime.

The most important stage of the repair work for ROF No. 1 was the replacement of two gate valves, which are pipeline valves used to shut off water flow in the mains.

“These valves have already served their useful life, so we dismantled them and installed new ones – smaller and more modern and functional. At the same time, we installed new valves in six process sections. This is necessary to ensure that water supply to them can be cut off in case of planned or unplanned shutdowns,” commented Oleksandr Golovko, Deputy Head of ROF No. 1 for Engineering.

During the shutdown, employees at ROF No. 2 also worked efficiently. Here, they replaced sections of the pipeline and the valve of water supply system No. 7, as well as sections of the pipeline leading to vacuum filters. They also replaced the hydraulic discharge pipeline, valves of the six-jet pulverizer and shut-off valves of the pump room.

The specialists also repaired components and equipment at slurry pumping station No. 1. Nine bottom valves and a rotary gate valve at the stationary pumping station were replaced, and the water supply system was restored.

After the scheduled three-day repairs, the equipment was launched on time.

Earlier, Northern Mining and Processing Plant allocated UAH 17 million to upgrade the LURGI 552A roasting machine in the pelletizing shop No. 2. In early October, the updated unit was put into operation after a quarterly overhaul.

  • Industry

Spanish Unesid insists on strengthening protection of European steel industry

Spanish steelmakers are calling on the EU to strengthen protection for the sector and help…

Tuesday June 3, 2025
  • Global Market

Turkey updates the system of state support for investments in the steel sector

On May 31, 2025, a new presidential decree on state support for investment came into…

Tuesday June 3, 2025
  • Global Market

Canadian steel producers call for immediate response to Trump’s tariffs

On May 31, 2025, Catherine Cobden, President and CEO of the Canadian Steel Producers Association…

Tuesday June 3, 2025
  • Companies

Erdemir announces large-scale investments in green transformation by 2050

Turkish steel company Erdemir has unveiled an updated sustainability strategy, according to which it plans…

Tuesday June 3, 2025
  • Global Market

India prioritizes local steel for government projects

The Indian government has revised its local steel policy for 2025 to ensure that locally…

Monday June 2, 2025
  • Companies

Zaporizhstal increased its rolled steel output by 4.9% y/y in January-May

Zaporizhstal Iron and Steel Works increased rolled steel production by 4.9% year-on-year – to 1.098…

Monday June 2, 2025