Northern Mining upgrades equipment at ore dressing plants No. 1-2

Metinvest Group’s Northern Mining and Processing Plant (Northern Mining) has completed the planned work at its ore dressing plants (ROF) No. 1 and 2 and slurry pumping station No. 1 during a three-day annual shutdown. It is reported by Metinvest.Media.

“We have started the planned shutdown of the slurry pumping station of the technical water supply and sludge management shop for repair. The main tasks include the replacement, repair, inspection and maintenance of pumping equipment, valves, water supply pipelines, etc.”, the statement said.

The main goal of the planned shutdown is to stabilize the operation of technical water supply systems. Particular attention is being paid to the equipment involved in this process, as its replacement is possible only if the processing complex – ROF No. 1, 2 and PCP No. 1 – is completely shut down. The plant’s specialists have diagnosed all the equipment in advance and identified what needs to be restored. To ensure efficient operation of the equipment, they planned the required amount of repairs to avoid further emergency downtime.

The most important stage of the repair work for ROF No. 1 was the replacement of two gate valves, which are pipeline valves used to shut off water flow in the mains.

“These valves have already served their useful life, so we dismantled them and installed new ones – smaller and more modern and functional. At the same time, we installed new valves in six process sections. This is necessary to ensure that water supply to them can be cut off in case of planned or unplanned shutdowns,” commented Oleksandr Golovko, Deputy Head of ROF No. 1 for Engineering.

During the shutdown, employees at ROF No. 2 also worked efficiently. Here, they replaced sections of the pipeline and the valve of water supply system No. 7, as well as sections of the pipeline leading to vacuum filters. They also replaced the hydraulic discharge pipeline, valves of the six-jet pulverizer and shut-off valves of the pump room.

The specialists also repaired components and equipment at slurry pumping station No. 1. Nine bottom valves and a rotary gate valve at the stationary pumping station were replaced, and the water supply system was restored.

After the scheduled three-day repairs, the equipment was launched on time.

Earlier, Northern Mining and Processing Plant allocated UAH 17 million to upgrade the LURGI 552A roasting machine in the pelletizing shop No. 2. In early October, the updated unit was put into operation after a quarterly overhaul.

  • Companies

Arvedi Group raises €900 million to expand production and decarbonize

Italian steel company Arvedi Group has raised €900 million in financing to implement a large-scale…

Friday June 27, 2025
  • Global Market

Domestic demand for steel in China continues to fall

Domestic demand for steel in China, according to market participants' estimates, continued to fall in…

Friday June 27, 2025
  • Industry

Construction works performed in Ukraine in January-April fell by 13% y/y

The index of construction work performed in Ukraine in January-April 2025 decreased by 13% compared…

Friday June 27, 2025
  • Global Market

Emissions in China’s steel industry sector rose by 17.9% y/y in May

In May 2025, Chinese steel enterprises belonging to the CISA industry association increased their total…

Friday June 27, 2025
  • Industry

The European Commission has adopted a new state aid system for clean industry

On June 25, the European Commission adopted a new state aid system to support the…

Friday June 27, 2025
  • Industry

Ukraine reduced iron ore exports by 13% y/y in January-May

Ukraine's mining industry reduced iron ore exports by 12.8% year-on-year in January-May 2025 compared to…

Friday June 27, 2025