Last year, Metinvest Group’s Northern Mining and Processing Plant (Northern GOK) allocated more than UAH 42 million to overhaul 4.5 km of railway tracks. Metinvest.Media reports.

Last year, the company overhauled 4.2 km of tracks and 12 sets of switches located on the territory of Pervomaisky open pit mine and the finished goods export shop of the railway transport department to ensure the reliability of rail transportation.

The upgrade involved the complete dismantling of the old track, cleaning of the rail and sleeper grid and laying of the track using machinery.

Olexander Skiba, head of the track maintenance and repair shop at Northern Mining’s railroad department, noted that the railroad is a key component of the plant’s logistics, and a significant amount of cargo is delivered by these routes.

According to him, the amount of work carried out by the shop last year was 1.5 times higher than in 2023.

“The last time the tracks and switches were repaired was more than 15 years ago, so there was a need for a large-scale restoration, which the shop team carried out during the year. Our employees ensure the stable operation of the railway: the division’s teams ensure the safe transportation of ore and overburden from the pits, as well as finished products throughout the year. All the measures taken are aimed at upgrading the shop’s capacities and ensuring efficient operation in the future,” summarized Skiba.

Currently, the length of the extensive track network at Northern Mining is almost 300 km. The track maintenance and repair shop established in 2022 takes care of them. More than 500 railroad switches are also under the attention of specialists. Alongside the overhauls, the shop’s teams carry out the relevant routine maintenance work on an ongoing basis.

The company’s plans for the current year include the restoration of 5.7 km of tracks and 18 turnouts. The work will be carried out at the Pervomaisky and Ganovsky quarries and at the finished goods export shop of the UZT.

Last fall, Northern Mining upgraded the equipment of ore processing plants No. 1-2.

  • State

The Verkhovna Rada has ratified the agreement on a free trade area with Turkey

On 14 July 2026, the Verkhovna Rada of Ukraine passed a law ratifying the Free…

Tuesday July 14, 2026
  • Industry

Ukraine increased imports of long steel products by 72.6% y/y in January–May

Between January and May 2026, the long steel products market in Ukraine saw a significant…

Tuesday July 14, 2026
  • Global Market

Formosa is further reducing its prices for hot-rolled steel for large orders

Less than a week after its previous price cut for hot-rolled steel, the Vietnamese producer…

Tuesday July 14, 2026
  • Infrastructure

Tosyalı has raised €187 million for a solar power development project

The Spanish bank BBVA has provided the Turkish steel group Tosyalı with €187 million in…

Tuesday July 14, 2026
  • Global Market

China’s steel exports fell by 5.6% y/y in January–June

In the first half of 2026, China’s steel exports fell by 5.6% year-on-year to 54.87…

Tuesday July 14, 2026
  • Global Market

Tokyo Steel has left its prices for steel products unchanged for August sales

Tokyo Steel, a leading Japanese electric arc furnace steel producer, has left its prices for…

Tuesday July 14, 2026