Kametstal performs 45-foot overhaul with mixer refutations

Kametstal Iron and Steel Works began one of the most ambitious repairs of 2024 – a 45-day overhaul with the refueling of the mixer. This is stated in the press release of the enterprise.

The unit with a capacity of 2.5 thousand tons performs the technological preparation of liquid cast iron – equalizing the temperature and averaging the chemical composition before it is supplied to the converter compartment and poured into the converters.

«During a stop to perform repair work on the mixer, the production of steel in the workshop continues: the transfusion of cast iron from the cast iron buckets of the blast furnace shop into the cast iron buckets of the converter shop is performed directly, bypassing the mixer,» the company notes.

The main part of the overhaul is the complete replacement of the fire-resistant masonry of the mixer body, which since the previous overhaul in 2021 has defended its normative service life. Now the old lining has been dismantled, the building has been examined and prepared for the lining works, which have already been started by specialist contractors. In total, it is planned to update 550 cubic meters of masonry.

During the overhaul, key equipment is also restored, repair interventions in which are possible only during a complete long stop of the unit – in particular, the revision and repair of the drive mechanism, the mixer swing mechanism, the tightening of the bolt fasteners of the covers, etc.

Employees of the electrical and power services also began a comprehensive repair and maintenance of the aspiration system of the mixer: they restore the electric motor with a capacity of 930 kW, conduct a thorough audit of the aspiration path – dampers, electrical equipment, smoke pump units, etc.

«Despite the economic, technical and logistical difficulties of wartime, the company invests in the restoration of important equipment of Kametstal, on the reliable functioning of which depends the stable and efficient operation of the converter shop and the entire enterprise. High-quality performance of the planned overhaul of the mixer will extend the life of its operation and bring the operation of the unit as close as possible to the passport characteristics, «summarizes the plant.

As GMK Center reported earlier, in June, Kametstal announced the overhaul of the air separation unit KAr-30 No. 3 in the oxygen compressor shop. The unit provides oxygen and nitrogen processes in the main production units, primarily the converter and blast furnace.

  • Global Market

The EU’s requirement regarding the smelting and casting of steel will come into force in October

On 24 June, the European Union published a regulation on new safeguard measures concerning steel…

Wednesday June 24, 2026
  • Industry

Exports of flat steel from Ukraine fell to 695.1 thousand tonnes in January–May

In January–May 2026, Ukraine’s steel companies reduced their exports of flat-rolled steel by 3.1% compared…

Wednesday June 24, 2026
  • Global Market

Global pig iron production fell by 2.8% y/y in January–May

Global pig iron production for the period January–May 2026 fell by 2.8% compared with the…

Wednesday June 24, 2026
  • Global Market

SSAB Americas is launching a steel recycling project in the US

The steel company SSAB Americas, together with its partners The Greenbrier Companies and Alter Trading,…

Wednesday June 24, 2026
  • Global Market

British steel fabricators are calling for the new steel measures to be revised

The new quotas and import duties on steel introduced by the UK government to support…

Wednesday June 24, 2026
  • Industry

Ukrainian Railways has launched a programme to sell scrap in the form of worn-out carriages

In May, Ukrainian Railways (UZ) launched its previously announced programme to sell large quantities of…

Wednesday June 24, 2026