Kametstal performs 45-foot overhaul with mixer refutations

Kametstal Iron and Steel Works began one of the most ambitious repairs of 2024 – a 45-day overhaul with the refueling of the mixer. This is stated in the press release of the enterprise.

The unit with a capacity of 2.5 thousand tons performs the technological preparation of liquid cast iron – equalizing the temperature and averaging the chemical composition before it is supplied to the converter compartment and poured into the converters.

«During a stop to perform repair work on the mixer, the production of steel in the workshop continues: the transfusion of cast iron from the cast iron buckets of the blast furnace shop into the cast iron buckets of the converter shop is performed directly, bypassing the mixer,» the company notes.

The main part of the overhaul is the complete replacement of the fire-resistant masonry of the mixer body, which since the previous overhaul in 2021 has defended its normative service life. Now the old lining has been dismantled, the building has been examined and prepared for the lining works, which have already been started by specialist contractors. In total, it is planned to update 550 cubic meters of masonry.

During the overhaul, key equipment is also restored, repair interventions in which are possible only during a complete long stop of the unit – in particular, the revision and repair of the drive mechanism, the mixer swing mechanism, the tightening of the bolt fasteners of the covers, etc.

Employees of the electrical and power services also began a comprehensive repair and maintenance of the aspiration system of the mixer: they restore the electric motor with a capacity of 930 kW, conduct a thorough audit of the aspiration path – dampers, electrical equipment, smoke pump units, etc.

«Despite the economic, technical and logistical difficulties of wartime, the company invests in the restoration of important equipment of Kametstal, on the reliable functioning of which depends the stable and efficient operation of the converter shop and the entire enterprise. High-quality performance of the planned overhaul of the mixer will extend the life of its operation and bring the operation of the unit as close as possible to the passport characteristics, «summarizes the plant.

As GMK Center reported earlier, in June, Kametstal announced the overhaul of the air separation unit KAr-30 No. 3 in the oxygen compressor shop. The unit provides oxygen and nitrogen processes in the main production units, primarily the converter and blast furnace.

Share
Published by
Masha Malonog
Tags: capital investment Metinvest Kametstal
  • Companies

Interpipe increased pipe sales by 32% y/y in 2024

In 2024, Ukrainian industrial company Interpipe increased its sales of tubular products by 32% compared…

Wednesday June 4, 2025
  • Global Market

Square billet prices lost up to $10 per ton in May

Prices for square billets on most regional markets in May were quite stable, with a…

Wednesday June 4, 2025
  • State

Currency restrictions are a key obstacle to investment – Vodoviz

At the Forbes Money forum held on May 30, 2025, in Kyiv, business and government…

Wednesday June 4, 2025
  • Global Market

India considers increasing protective duty on steel imports to 24%

The Indian government is assessing the possibility of raising the safeguard duty on steel to…

Tuesday June 3, 2025
  • Global Market

Iron ore prices fell by 2% last week

Last week, from May 24 to 31, 2025, global iron ore prices showed a downward…

Tuesday June 3, 2025
  • Industry

Cargo owners have identified key problems when working with Ukrainian Railways

The biggest problems of cargo owners during rail transportation are the inflexibility of pricing by…

Tuesday June 3, 2025