Kametstal modernizes Ladle Furnace No. 1 in BOF Shop

As part of its scheduled overhaul, Kametstal has upgraded Ladle Furnace No. 1 (LF-1), which plays a key role in the out-of-unit steel finishing process. The work was focused on improving equipment reliability and preventing emergency shutdowns in the future, according to a press release from the company.

The centerpiece of the repair was the replacement of the water-cooled vault, an important component that prevents secondary oxidation of the metal and emissions of slag or steel from the ladle. It is the efficiency of this part of the plant that determines the stability of the temperature regime and the quality of the processed steel.

According to Yevgeniy Tkatsevich, Senior Foreman of the Out-of-Aggregate Finishing Shop, after dismantling and defecting, an optimization decision was made not to buy a new vault but to restore the existing one. Thanks to the coordinated work of the metallurgical equipment repair specialists and technical services of the shop, the damaged elements were completely replaced, and the unit was assembled, centered, connected to power and tested.

At the same time, infrastructure repairs were carried out, which are only possible during the shutdown of CCM-1: the steel carrier was replaced, a 35 kW transformer was inspected, the cooling reactor was upgraded and a new vacuum chamber was installed.

After the repairs were completed, CCM-1 was successfully put into operation and operates steadily, alternating with CCM-2, ensuring production continuity and compliance with quality standards.

As GMK Center previously reported, Kametstal has started overhauling one of the key units of its steelmaking operations, BOF vessel No. 1. The work is being carried out as part of the 2025 overhaul program with a focus on upgrading the main equipment and power systems.

  • Сonferences

ANNOUNCEMENT: Mining and Metals Central Asia 2025

On September 17-19, Almaty (Kazakhstan) will host the 30th anniversary Central Asian international exhibition of…

Tuesday July 1, 2025
  • Companies

The highest electricity price in Europe may shut down ArcelorMittal Kryvyi Rih

ArcelorMittal Kryvyi Rih, Ukraine's largest steel mill, is at risk of closing due to the…

Tuesday July 1, 2025
  • State

The government forecasts Ukraine’s GDP growth to accelerate to 4.5% in 2026

The budget declaration for 2026-2028, approved by the government on June 27, provides for an…

Tuesday July 1, 2025
  • Global Market

Iron ore prices fluctuate around $100/t

As of June 27, 2025, September iron ore futures on the Dalian Commodity Exchange (DCE)…

Tuesday July 1, 2025
  • Global Market

Inflation in the eurozone accelerated to 2% in June

Inflation in the eurozone rose by 2% in June 2025 compared to the same month…

Tuesday July 1, 2025
  • Global Market

The world is stepping up measures against dumped imports of steel products

Global players in the steel market are stepping up measures against dumped imports of metal…

Tuesday July 1, 2025