Kametstal has begun a series of major repairs to its rolling equipment

The Kametstal steel plant (Metinvest Group) has launched a series of major overhauls of its main rolling equipment as part of its 2025 program. The first object of the large-scale upgrade was the pipe mill, which produces SVP-27 mine props and blanks for large-diameter grinding balls, according to a press release.

The main focus of the repair work is on restoring the electrical, power, and mechanical equipment of key sections. These are the units that require a long shutdown of the mill, so intervention is only possible during major repairs.

In particular, the rolling mill section is undergoing an upgrade of the manipulator lines, replacement of the electrical panels of the heating furnaces and guide inserts of the 900 mill. At the same time, a complete inspection of the components of the first, second, and third 750 mills is being carried out, with the necessary repairs being made.

On the roller table of the pipe mill, bearings and rollers worn out during many years of operation are being replaced to ensure the stability of the rolling movement. A separate area of focus is the modernization of the water supply system, in particular, the replacement of a section of the pipeline, which will create a backup inlet and ensure uninterrupted water supply for technological needs.

In addition, rolling mill employees are cleaning the hydraulic tunnel of scale that has accumulated over a long period of time and prevented the effective drainage of technical water.

This overhaul is of strategic importance for both the workshop and the entire enterprise. It is aimed at improving the reliability of the pipe mill, which produces SVP-27 profile rolled products for the mining industry. At the same time, the section remains an important link in the production of blanks for large-diameter grinding balls, which are in stable demand on the market.

It should be noted that Kametstal plans to invest UAH 2.5 billion ($59.8 million) in production capacity in 2025, which is a record amount in recent years. The most ambitious project is the overhaul of DP-9, which received a third of the program’s total budget. In total, the plant plans to implement 114 investment projects during the year.

  • Industry

Exports of flat steel from Ukraine fell to 695.1 thousand tonnes in January–May

In January–May 2026, Ukraine’s steel companies reduced their exports of flat-rolled steel by 3.1% compared…

Wednesday June 24, 2026
  • Global Market

Global pig iron production fell by 2.8% y/y in January–May

Global pig iron production for the period January–May 2026 fell by 2.8% compared with the…

Wednesday June 24, 2026
  • Global Market

SSAB Americas is launching a steel recycling project in the US

The steel company SSAB Americas, together with its partners The Greenbrier Companies and Alter Trading,…

Wednesday June 24, 2026
  • Global Market

British steel fabricators are calling for the new steel measures to be revised

The new quotas and import duties on steel introduced by the UK government to support…

Wednesday June 24, 2026
  • Industry

Ukrainian Railways has launched a programme to sell scrap in the form of worn-out carriages

In May, Ukrainian Railways (UZ) launched its previously announced programme to sell large quantities of…

Wednesday June 24, 2026
  • Global Market

India will monitor imports of Chinese steel before introducing new restrictions

India will continue to monitor steel imports for at least another two months before considering…

Wednesday June 24, 2026