Kametstal carries out overhaul of converter No. 1 with renewal of key systems

Kametstal, a Metinvest Group steelmaker, has launched a major overhaul of one of its key steelmaking units, BOF vessel No. 1. The work is being carried out as part of the 2025 overhaul program with a focus on updating the main equipment and power systems, the company said in a statement.

The main focus is on the modernization of the gas exhaust system. In particular, the tuyere and auxiliary caissons, the lower part of the main caisson (the “skirt”), and protective screens are to be replaced. At the same time, the stator and rotor of the flue gas blower electric motor are being replaced.

An important stage has already been completed – the repair of the converter body to restore its tightness. This made it possible to proceed to a complex operation – turning the support bearing. After lifting more than 1,000 tons of the vessel, the specialists will turn the outer cage of the bearing, which will extend its service life. The lubrication system will also be inspected and updated.

Among the important tasks is the complete replacement of the refractory lining. The dismantling of old materials has already been completed.

According to Andriy Zuev, Deputy Head of the BOF Shop for Engineering, the repairs cover not only the main equipment but also the entire infrastructure of the unit: oxygen supply machines, pumping units, vertical ducts, steel carriers and slag carriers. The work is being carried out in all areas – mechanical, power and electrical – to ensure safe and stable operation of the BOF vessel after the repair is completed.

As a reminder, Kametstal has started one of the largest overhauls under the 2025 program – the second overhaul of blast furnace No. 9 (BF-9). The main work is focused on upgrading critical components of the unit to improve its performance and reliability.

In 2025, the company plans to invest UAH 2.5 billion ($59.8 million) in production facilities, which is a record amount in recent years. The largest project is the overhaul of BF-9, which will receive a third of the program’s total budget. In total, the plant plans to implement 114 investment projects during the year.

  • Global Market

Kazakhstan increased steel production by 7.5% m/m in May

In May 2026, Kazakhstan increased its steel production by 7.5% month-on-month and by 6.2% year-on-year,…

Friday June 19, 2026
  • Global Market

Voestalpine is expanding its environmental modernisation programme at its plant in Donawitz

The Austrian steel and technology group voestalpine has unveiled plans for the next phase of…

Friday June 19, 2026
  • Global Market

China is increasing its imports of coking coal following a mining accident in Shanxi

Imports of coking coal into China are set to continue growing in 2026. The main…

Friday June 19, 2026
  • Industry

Ukraine increased exports of semi-finished products by 41.6% m/m in May

In May 2026, Ukraine’s steelworks increased their exports of semi-finished steel products by 41.6% compared…

Friday June 19, 2026
  • Global Market

Italy increased steel production by 4.9% m/m in May

Italian steelworks increased steel production by 4.9% in May 2026 compared with the previous month,…

Thursday June 18, 2026
  • State

The National Bank of Ukraine has kept its base rate at 15 per cent

The National Bank of Ukraine (NBU) has kept its policy rate at 15 per cent.…

Thursday June 18, 2026