Central Mining upgrades main conveyors with modern drive systems

The crushing plant at Central Mining and Processing Plant (Central Mining and Processing Plant, Metinvest) is continuing its program to upgrade the drive gearboxes of its conveyors. The program began two years ago with the replacement and repair of components of the K-2 main conveyor, which is one of the factory’s key transport lines, according to a statement from Metinvest.Media.

In 2025, the company is continuing this work. Currently, one of the gearboxes is undergoing major repairs, and another unit has been completely replaced with a new set manufactured by the German company SEW-EURODRIVE. This is already the third project of cooperation between the crushing plant and this equipment supplier.

“A completely new drive system with a gearbox replaces the outdated mechanism on our largest M-1 conveyor. It is used to transport ore from the second crushing stage to the third,” said Anton Milkevich, deputy head of engineering at the crushing plant.

According to him, the manufacturer took into account all the wishes of the mechanics and electricians of the Central Mining, so the equipment fully meets the requirements of the production process. Among the important advantages is a significantly reduced weight. The new set weighs only 5 tons compared to 15 tons for the previous one.

“The reduction in weight greatly simplifies installation, adjustment, and further maintenance. In addition, SEW-EURODRIVE gear units have proven themselves in terms of power, convenience, and reliability, even in the harsh conditions of the crushing plant,” emphasized Sergiy Mokhtan, chief mechanic of the plant.

Next year, the plant plans to complete the program by replacing the last of the five gearboxes. The main goal of the upgrade is to prevent emergency equipment shutdowns, ensure a stable production rhythm, and improve employee safety.

In May, Central Mining completed a three-week repair campaign costing almost UAH 40 million. During the shutdown, major and maintenance repairs were carried out on key production units, including the calciner, cup grate, smoke extractor No. 2, three conveyor belts, and excavators.

  • Infrastructure

Businesses purchased the entire volume of electricity at the first long-term auctions

The first electricity auctions under the new long-term contract mechanism have taken place in Ukraine.…

Monday July 13, 2026
  • Global Market

India has extended the anti-dumping duty on imports of seamless pipes from China

India has extended the anti-dumping duty on imports of seamless pipes, tubes and hollow sections…

Monday July 13, 2026
  • Companies

Jingye Steel will insist on full compensation for the takeover of British Steel

China’s Jingye Steel has stated that it will demand prompt, adequate and effective compensation from…

Monday July 13, 2026
  • Global Market

EU decision on steel quotas poses further challenges for Ukraine – Politico

On 1 July, new EU safeguard measures on steel came into force after the European…

Monday July 13, 2026
  • Global Market

JSW Italy has reached an agreement with the Italian government on the development of the Piombino steelworks

The Italian Ministry of Economic Development (Mimit) has reached an agreement with JSW on the…

Monday July 13, 2026
  • Global Market

Baosteel is raising prices for hot-rolled steel for August sales

Baoshan Iron & Steel (Baosteel), a subsidiary of the world’s leading steel producer China Baowu…

Monday July 13, 2026