Central Mining allocated over UAH 28 million to upgrade railroad tracks

Central Mining and Processing Plant (Central GOK), a part of Metinvest Group, is carrying out overhaul of railway tracks, allocating more than UAH 28 million for this purpose. This is stated in the press release of Metinvest.Media.

By the end of the year, repair crews plan to upgrade nearly 1.5 km of railroad tracks.

In general, Central GOK has an extensive system of railways with a total length of 270 km. This year, in addition to routine maintenance and repairs, the specialists of the Track and Yard Shop of the Railway Transport Department of the Centralized Plant are carrying out major overhauls of a number of tracks and turnouts.

Currently, 400 meters of track have been overhauled on the section between Rokuvata and Administrative Center stations. Last month, work continued at Unloading station: track No. 2 and track No. 6 were replaced, both 200 meters long. Also, 200 meters of track were restored in the direction of Artemivka quarry: on the Artemivka – Vidvalna stretch. The railway workers also repaired five turnouts: three at Industrial Site station and one turnout each at Unloading and Artemivka.

“Railways are an important component of production logistics, as the majority of cargo is delivered to the plant by rail, and the key to efficient transportation is primarily the condition of the tracks. This fall’s work is large-scale, involving the overhaul of almost 1.5 km of tracks. In particular, this will ensure the safety and reliability of traffic on the routes for the delivery of ore from the open pits and Kolachevsky mine to the crushing plant, as well as during the transportation of other goods for production needs,” said Olexander Mukha, Head of the Railway Transport Department of the Central Mining and Processing Plant.

Earlier, Central GOK allocated UAH 2.4 million to upgrade the equipment of the crushing plant. The company replaced the crushing cone of the KKD 1500/180 crusher, which is one of the largest units of the crushing plant. It is responsible for the first stage of crushing ore from the open pit. The next stage of repairs is to replace the belt on the K-1 conveyor.

  • Companies

Celsa considers selling Polish plant Huta Ostrowiec

Spanish steelmaker Celsa ended 2024 with losses of €281 million and is considering selling its…

Tuesday July 1, 2025
  • Global Market

Nucor raised prices for hot-rolled coil by $10/t

US steel company Nucor announced an increase in the weekly spot price (CSP) for hot-rolled…

Tuesday July 1, 2025
  • Companies

Central Mining modernized its pelletizing plant at a cost of UAH 40 million

A three-week repair campaign costing almost UAH 40 million has been completed at the pelletizing…

Tuesday July 1, 2025
  • Companies

SSAB has secured an additional €430 million for its green transformation in Luleå

Swedish steel company SAAB has announced that it has secured an additional €430 million in…

Tuesday July 1, 2025
  • Industry

Ukraine reduced semi-finished products’ exports by 34% y/y in January-May

In January-May 2025, Ukrainian steel companies reduced exports of semi-finished steel products by 34.1% compared…

Tuesday July 1, 2025
  • Society

Metinvest to allocate over $500 thousand to support veterans in 2025

Metinvest Group, which has faced the mobilization of one in five employees since the start…

Tuesday July 1, 2025