ArcelorMittal Kryvyi Rih is shutting down production due to logistics issues

ArcelorMittal Kryvyi Rih PJSC announced the shutdown of part of its mining and steelmaking operations due to systemic disruptions in raw material supplies from Ukrainian Railways JSC (UZ). This was stated in a press release.

According to the company, over the past month, the enterprise has not been receiving the necessary volumes of fluxes, which has led to a critical decline in inventories. This has already affected the stable operation of key units. At the same time, problems arose with the shipment of iron ore concentrate, which led to the suspension of ore mining.

As a result, the company was forced to shut down one of its two blast furnaces, two sintering machines, and the ore processing plant. The company warns that if supplies do not improve in the coming days, the second blast furnace, as well as other production facilities, may also be shut down.

The company’s CEO, Mauro Longobardo, noted that the situation is a result of inadequate transportation planning. According to him, the company is not receiving critically important raw materials for pig iron production and is also unable to ship its own products.

“For our company, which has been operating at a loss for four years now, another supply issue could be fatal,” he emphasized, adding that operations are also under pressure from high electricity prices, the introduction of CBAM, and rising imports.

The company stresses that the situation is already having a direct impact on production performance and tax revenues. At the same time, according to the company, Ukrainian is focusing on raising tariffs instead of ensuring the stability of transportation.

ArcelorMittal Kryvyi Rih called for immediate action to restore shipments and warned of the risks of systemic consequences for Ukraine’s entire mining and metallurgical industry should the situation continue to deteriorate.

As a reminder, ArcelorMittal Kryvyi Rih lost 300,000 tons of steel exports due to CBAM in the first quarter of 2026, according to Mauro Longobardo’s column for GMK Center. In 2026, the company had planned to ship 1.2–1.25 million tons to Europe—nearly half of its total steel production—but this market has been lost.

  • Infrastructure

Businesses purchased the entire volume of electricity at the first long-term auctions

The first electricity auctions under the new long-term contract mechanism have taken place in Ukraine.…

Monday July 13, 2026
  • Global Market

India has extended the anti-dumping duty on imports of seamless pipes from China

India has extended the anti-dumping duty on imports of seamless pipes, tubes and hollow sections…

Monday July 13, 2026
  • Companies

Jingye Steel will insist on full compensation for the takeover of British Steel

China’s Jingye Steel has stated that it will demand prompt, adequate and effective compensation from…

Monday July 13, 2026
  • Global Market

EU decision on steel quotas poses further challenges for Ukraine – Politico

On 1 July, new EU safeguard measures on steel came into force after the European…

Monday July 13, 2026
  • Global Market

JSW Italy has reached an agreement with the Italian government on the development of the Piombino steelworks

The Italian Ministry of Economic Development (Mimit) has reached an agreement with JSW on the…

Monday July 13, 2026
  • Global Market

Baosteel is raising prices for hot-rolled steel for August sales

Baoshan Iron & Steel (Baosteel), a subsidiary of the world’s leading steel producer China Baowu…

Monday July 13, 2026